School URN 121466 Conversion On hold

Riverside Community Primary School

Conversion date
25 October 2027 provisional
Incoming trust
Not provided
LA and region
Norfolk, East Of England

Task list

Project kick-off

Handover with regional delivery officerNot started
External stakeholder kick-offNot started
Confirm the academy's risk protection arrangementsNot started
Check accuracy of high needs places informationNot started
Complete a notification of changes to funded high needs places formNot started
Process conversion support grantNot started
Confirm and process the sponsored support grantNot started
Confirm the academy nameNot started
Confirm the headteacher's detailsNot started
Confirm the chair of governors' detailsNot started
Confirm the incoming trust CEO's detailsNot started
Confirm the main contactNot started
Confirm the proposed capacity of the academyNot started

Get ready for opening

Confirm the school has completed all actionsNot started
Confirm all conditions have been metNot started
Share the information about openingNot started

After opening

Confirm the academy open dateCompleted
Redact and send documentsNot started
Receive declaration of expenditure certificateNot started

Completing a project

You should only complete the project when you have finished every task and marked any that are not needed as not applicable.

You will not be able to change this project once it is completed.

Complete project

Resume the project

You can resume the project if you are ready to continue with it.

Resume the project